Project Title: EPC For Balance Of Plant (BOP) Works For Habshan P5 Short Term Facilities Project
Project Location: Habshan
Client: Robt Stone
End User: ADNOC Gas
Project Description: To deliver full civil engineering support for the BAB CDS scope, including IFR/IFA/IFC/As-Built deliverables, structural adequacy checks, integration of interface contractor data, and participation in all project reviews and workshops. All civil IFC deliverables must be completed and approved by January 2026 to meet the planned March 2026 shutdown execution.
Scope of Work:
Project Status: Ongoing
Start Year: 2025